This page is the compact contract for how project lifecycle state and review state advance across a tracked OAT project.

Quick Look

  • What it does: defines the allowed lifecycle and review-state transitions recorded in state.md and plan.md.
  • When to use it: when you need to debug lifecycle routing, review posture, or why a project is not advancing to the next phase.
  • Primary artifacts: state.md, plan.md, implementation.md

State Transition Map

The solid chain is the spec-driven progression. Lite, brief and goal enter at Plan in progress and never set oat_phase to discovery, spec, or design; quick and import projects also skip part of the leading chain. Goal adds a milestone state machine inside implementation, described under Goal progression.

Phase status values

oat_phase_status in state.md:

  • in_progress — phase is actively being worked on
  • complete — phase is finished
  • pr_open — post-PR review posture. Set by oat-project-pr-final. Agents should route to oat-project-revise (for feedback) or oat-project-complete (when approved).

pr_open is not the source of truth for actual PR existence. That is tracked separately in state.md via:

  • oat_pr_status — PR lifecycle state (ready, open, closed, merged)
  • oat_pr_url — tracked PR URL when a PR exists

Lifecycle progression

Typical progression:

  1. Discovery in progress
  2. Ready for spec
  3. Spec in progress
  4. Ready for design
  5. Design in progress
  6. Ready for plan
  7. Plan in progress
  8. Ready for implement
  9. Implement in progress
  10. Implement complete (final review passed)
  11. PR open (pr_open) — post-PR review posture; actual PR existence is tracked via oat_pr_status / oat_pr_url. pr_open is a valid posture for the completion journal check
  12. Revision loop (optional): pr_open → revise → in_progress → implement → pr_open
  13. Complete — oat project journal check --at completion passes (terminal journal shape: every plan task block completed with commit evidence or an authorized override, terminal run lines, receipts and deferrals in their slots, no template residue), then oat project complete-state rechecks the closeout invariant and that evaluator before it writes; oat_pr_status_observed_at records when the archived PR fields were observed

Lite progression:

  1. Plan in progress (oat_workflow_mode: lite, oat_phase: plan)
  2. Ready for implement (one approval; no discovery, spec, or design states)
  3. Implement in progress (single phase, no HiLL checkpoint pauses)
  4. Implement complete (final review passed)
  5. PR open (pr_open) — lite closeout routes straight to oat-project-pr-final
  6. Complete

A lite project that outgrows one sitting can move to the quick chain with oat project promote <project-path> --to quick, which flips oat_workflow_mode to quick and sets oat_phase: discovery with oat_phase_status: complete. See Lifecycle.

Brief progression:

  1. Plan in progress (oat_workflow_mode: brief, oat_phase: plan) — oat-project-brief owns the interview, the artifact review, any configured gate, and the single approval
  2. Ready for implement (plan.md complete and pointing to oat-project-implement)
  3. Implement in progress — progress counts phase-units; a phase is accepted only by **Status:** completed under its heading in implementation.md
  4. Implement complete (final review passed). While any phase-unit is provisional or unaccepted, the router's brief-unit guard sends the project back to oat-project-implement ("Incomplete phase-units remain in the active scope") before every later check
  5. PR open (pr_open) through the same post-implementation sequence as quick
  6. Complete

A brief project can move to the quick chain with oat project promote <project-path> --to quick; quick plan readiness stays false while oat_promotion_pending_phases lists phases that still need tasks. See Lifecycle.

Goal progression

A goal project runs the brief chain once per milestone. oat_phase and oat_phase_status keep their meaning; the milestone loop lives in its own state.md fields, owned as follows:

oat_milestone_statusMeaningNext owner and transition
aligningThe next milestone is being planned or awaits activationoat-project-goal activates it (implementing) after review, its plan carrier, approval, and the previous delivery observed at its agreed endpoint
implementingThe milestone's phase-units are executingImplement's milestone closeout runs the exit gate and writes reviewing
reviewingThe exit carrier is fresh; the integrated review is nextoat-project-review-receive writes delivering on a clean receive of the integrated review, or implementing when fixes are queued
deliveringA passed, fresh integrated review and exit carrieroat-project-pr-progress registers the delivery (dNN) and writes delivered; stale evidence sends it back to reviewing; oat-project-review-receive returns it to implementing when a delivery-time review queues fixes
deliveredThe delivery is registered, open and review-readyoat-project-goal re-aligns (aligning for the next milestone) once the delivery reaches its endpoint, or records the terminal declaration; oat-project-pr-progress returns it to reviewing when oat-project-goal hands back a stale delivery whose integrated review or exit carrier is no longer fresh

oat_goal_status is active until the user declares the goal met (declared_met) with an exhaustive oat_goal_outcome_audit. Recovery of an older milestone's delivery is recorded in oat_goal_recovery and never moves oat_milestone or its status. oat-project-revise may return the active milestone from delivered or delivering to implementing for inline feedback. The router reads only these persisted fields; delivery freshness comes from oat project delivery refresh and oat project delivery check.

delivered and the registry's at_endpoint are different: delivered means the pull request is registered and open, at_endpoint means it has reached the agreed endpoint (open or merged). Re-alignment may draft and approve the next milestone while a merged endpoint is pending, but activation waits for it. Terminal closeout (oat project closeout-check, oat project complete-state) requires the declaration, the audit and delivery coverage of every accepted phase. A goal project can move to quick at a settled delivery boundary; see Lifecycle.

Review progression

In plan.md Reviews table:

  • pending -> received -> fixes_added -> fixes_completed -> passed

Guardrail

Do not move to the next lifecycle state if review/state artifacts indicate unresolved gates.

Reference artifacts

  • .oat/projects/<scope>/<project>/state.md
  • .oat/projects/<scope>/<project>/plan.md (## Reviews, and ## Milestones for goal)
  • .oat/projects/<scope>/<project>/implementation.md

On this page